Status of DPRs for State Roads approved "In-Principle" as new NHs. Date :20/06/2025

S.No.DescriptionLength(Km)
1 Length of In-Principle NHs awarded to consultants for preparation of DPRs1031
2 Length of In-Principle NHs for which tender are progress 435
3 Length of In-Principle NHs taken over by NHAI107
 Total Length of In-Principle NHs as declared by the MORTH,Govt of India1573

Status of In-Principle NHs awarded to Consultants for preparation of DPRs Date :20/06/2025

S.No.Name of ProjectTotal Length (in Km)AgencyRemarks
1 Kodikonda Checkpost (on NH 44), Lepakshi,Hindupur, Madakasira55M/s Voyants Solutions Pvt LtdAgreement concluded vide Agt No.12/2016-17, dt:28.7.16. Work is in progress. MoRTH, vide t/o Lr dated: 18.7.16, was requested to approve the estimate submitted based on lowest quoted price and to communicate TA&FS.
2 Kadapa (on NH 40) -Rajampeta-Kodur-Renigunta (on NH 71)137M/s Feed Back Consultants Pvt LimitedTraffic Survey completed. Alignment proposals to be submitted by the Consultant.
3 Mydukuru (NH 40) -Porumamilla-Seetharampuram - Pamuru (NH 565) - Kandukuru - Singarayakonda (NH 16).   
i) Mydurkur-Porumamilla45M/s Egis IndiaTraffic Survey completed.Revised Alignment proposals to be submitted by the Consultant.
ii) Porumamilla - CS Puramu60M/s Voyants Solutions Pvt LtdAgreement concluded vide Agt No.13/2016-17, dt:28.7.16. Work is in progress. MoRTH, vide t/o Lr dated: 18.7.16, was requested to approve the estimate submitted based on lowest quoted price and to communicate TA&FS.
iii) CS Puramu - Singarayakonda90M/s K&J ProjectsAgreement concluded on 10.8.16. Work is in progress. MoRTH, vide t/o Lr dated: 18.7.16, was requested to approve the estimate submitted based on lowest quoted price and to communicate TA&FS.
4 TS/AP Border - Piduguralla-Narasaraopeta on NH 544-D -Chilakaluripeta on NH 16 - Chirala on NH 216 - Vodarevu107M/s EGIS IndiaTraffic Survey completed.Revised Alignment proposals to be submitted by the Consultant.
5 Bhadrachalam (on NH 30) in TS - TS/AP Border -Jeelugumilli - Jangareddygudem - Devarapalli -Upto Rajhamundry(on NH 16)60M/s Feed Back Consultants Pvt LimitedTraffic Survey completed. Alignment proposals to be submitted by the Consultant.
6 Bhimavaram on NH 165 - Tadepalligudem on NH 1632M/s K&J ProjectsAgreement concluded on 10.8.16. Work is in progress. MoRTH, vide t/o Lr dated: 18.7.16, was requested to approve the estimate submitted based on lowest quoted price and to communicate TA&FS.
7 Rajahmundry on NH 16 - Rampachodavaram-Koyyuru-Chinthapalli-Lambasinghi-Paderu-Araku-Srungavarapukota-Vijayanagaram on NH 26   
i) Rajahmundry on NH 16 - Rampachodavaram55M/s EGISTraffic Survey completed. Alignment proposals to be submitted by the Consultant.
ii) Rampachodavaram- Koyyuru85M/s K&J ProjectsAgreement concluded on 10.8.16. Work is in progress. MoRTH, vide t/o Lr dated: 18.7.16, was requested to approve the estimate submitted based on lowest quoted price and to communicate TA&FS.
iii)Koyyuru-Chinthapalli-Lambasinghi-Paderu140M/s Mukesh & Associates JV with ArtefactAgreement concluded vide Agt No.15/2016-17, dt:03.8.16. Work is in progress. MoRTH, vide t/o Lr dated: 18.7.16, was requested to approve the estimate submitted based on lowest quoted price and to communicate TA&FS.
iv)Paderu- Araku55M/s SATRAAgreement concluded vide Agt No.11/2016-17, dt:27.7.16. Work is in progress. MoRTH, vide t/o Lr dated: 18.7.16, was requested to approve the estimate submitted based on lowest quoted price and to communicate TA&FS.
v) Araku-Srungavarapukota55M/s. Feedback Infra Pvt. Ltd.Traffic Survey completed. Alignment proposals to be submitted by the Consultant.
vi) Srungavarapukota-Vijayanagaram on NH 2630M/s SATRAAgreement concluded vide Agt No.11/2016-17, dt:28.7.16.MoRTH, vide t/o Lr dated: 18.7.16, was requested to approve the estimate submitted based on lowest quoted price and to communicate TA&FS.
8 Kuppam on NH 42 - Kolar (on NH 75, KTK)25M/s Voyants Solutions Pvt LtdAgreement concluded vide Agt No.12/2016-17, dt:28.7.16. Work is in progress. MoRTH, vide t/o Lr dated: 18.7.16, was requested to approve the estimate submitted based on lowest quoted price and to communicate TA&FS.
 TOTAL1031  

Status of In-Principle NHs for which bids invitedDate :20/06/2025

S.No.Name of ProjectTotal Length (in Km)Remarks
1 Madakasira - Rolla - AP/Karnataka border55Negotiations with consultants is in progress
2 Muddanur on NH 67 - Kadapa on NH 4050Negotiations with consultants is in progress
3 Patchur on NH 46, TN - Kuppam22Negotiations with consultants is in progress
4 Palasa on NH 16- upto AP/Odisha border23Work awarded, Agreement to be concluded.
5 Suryapet on NH 65- Khammam - Ashwaraopet-Rajahmundry85Work awarded, Agreement to be concluded.
6 Jn of NH-69 near Chintamani connecting Chelur, Rayacheruvu in KTK - Tanakal(on NH 42)15Negotiations with consultants is in progress
7 Jn of NH-48 near Chitradurga connecting Chelkere, Pavagada in KTK and terminating at its Jn of NH-44 near Penukonda in AP26Negotiations with consultants is in progress
8 Jn of NH-150A near Molakalnuru (KTK)-Rayadurg-Ananthapur at Jn of NH-44110Negotiations with consultants completed, LOA to be issued.
9 Tumkur-Kortagere-Pavagada-kalyanadurg-Joining upto Veparalla49Negotiations with consultants is in progress
 TOTAL435