Click Here :   CM Dashboard Photo Gallery

6 LANE FLY-OVER Date :26/09/2017

S.No.ItemTotal Qty.CompletedBalanceUnit
1 Piles4174170Nos
2 Pile Caps.47452Nos
3 Piers and Abutments47389Nos
4 Pier & Abutment Caps472522Nos
5 Casting of wings & Spines20737161357Nos
6 Launching of Segments (Spanwise)46046Nos

Piles

Piles Caps

Piers and Abutments

Pier & Abutment Caps

Casting of wings & Spines

Launching of Segments (Spanwise)

4 LANE ROAD Date :26/09/2017

S.No.ItemTotal Qty.CompletedBalanceUnit
1 Sub grade282228220M
2 GSB282228220M
3 WMM282228220M
4 DBM 1282228220M
5 DBM 2512226202502M
6 BC512205122M

ROAD LEVEL BRIDGEDate :26/09/2017

S.No.ItemTotal Qty.CompletedBalanceUnit
1 Piles36360Nos
2 Pile Caps.990Nos
3 Piers and Abutments990Nos
4 Pier & Abutment Caps990Nos
5 Girders24204Nos
6 Slabs862Nos

Piles

Piles Caps

Piers and Abutments

Pier & Abutment Caps

Girders

Slabs

FINANCIAL TARGETDate :26/09/2017

S.No.ItemTotal AmountFinancial Progress AchievedBalanceUnit
1 Financial Target (Cr)282.4135.47146.93Rs(Cr)

Financial Target (Cr)