6 LANE FLY-OVER Date :21/06/2018

S.No.ItemTotal Qty.CompletedBalanceUnit
1 Piles4174170Nos
2 Pile Caps.47470Nos
3 Piers and Abutments47416Nos
4 Pier & Abutment Caps47407Nos
5 Casting of wings & Spines20731438635Nos
6 Launching of Segments (Spanwise)461333Nos

Piles

Piles Caps

Piers and Abutments

Pier & Abutment Caps

Casting of wings & Spines

Launching of Segments (Spanwise)

4 LANE ROAD Date :21/06/2018

S.No.ItemTotal Qty.CompletedBalanceUnit
1 Sub grade282228220M
2 GSB282228220M
3 WMM282228220M
4 DBM 1282228220M
5 DBM 2512226202502M
6 BC512205122M

ROAD LEVEL BRIDGEDate :21/06/2018

S.No.ItemTotal Qty.CompletedBalanceUnit
1 Piles36360Nos
2 Pile Caps.990Nos
3 Piers and Abutments990Nos
4 Pier & Abutment Caps990Nos
5 Girders24204Nos
6 Slabs862Nos

Piles

Piles Caps

Piers and Abutments

Pier & Abutment Caps

Girders

Slabs

FINANCIAL TARGETDate :21/06/2018

S.No.ItemTotal AmountFinancial Progress AchievedBalanceUnit
1 Financial Target (Cr)293.38150.54142.84Rs(Cr)

Financial Target (Cr)